Tren Maya: judge ordered the provisional suspension of construction of stretch 5 south

The claim for amparo filed by a group of divers points to the absence of a manifestation of environmental impact

Guardar
PLAYA DEL CARMEN QUINTANA ROO,
PLAYA DEL CARMEN QUINTANA ROO, 19ENERO2022.- Autoridades de Fonatur anunciaron la cancelación definitiva de las obras del Tren Maya en Playa del Carmen, acordaron que las vías férreas ya no pasarán por la ciudad sino por una nueva ruta por definir. La decisión de Fonatur responde a la petición de los empresarios playenses que evidenciaron lo improcedente de esta ruta. En la imagen se observa el trazo del Tramo 5 por donde iba a pasar el Tren Maya. FOTO: ELIZABETH RUIZ/CUARTOSCURO.COM

A judge in the state of Yucatán granted the provisional suspension of Section 5 south of the Maya Train after a group of divers filed a claim for amparo for not having a demonstration of environmental impact.

This was announced by the association Defending the Right to a Healthy Environment (DMAS) through a statement shared on its social networks, in which it is mentioned that after three weeks, the First District Court admitted the issue and notified them on Monday, April 18 of the suspension.

The agreement, dated April 12, provides for the suspension of any act aimed at continuing the construction of Section 5 South, which runs from Playa del Carmen to Tulum and covers an area of 60.3 kilometers, so that the execution of works related to its infrastructure will not be allowed, as well as the removal of destruction of the biodiversity of the area.

Infobae

The amparo was filed on Thursday, March 24, before the Ninth District Court by the DMAS and a group of speleologists and divers residing in Playa del Carmen, but was subsequently referred to the First Court through an agreement with the Council of the Federal Judiciary (CJF).

They pointed out that, even without counting the manifestation of environmental impact, deforestation took place in Playa del Carmen, Rio Secreto, Akumal and Tulum. They also indicated that this section will cross underground rivers that will be affected, since they run from west to east and the preliminary line is from north to south.

Meanwhile, the Ministry of Agrarian, Territorial and Urban Development (Sedatu), the Ministry of National Defense (Sedena) and the National Fund for the Promotion of Tourism (Fonatur) were the authorities requested, according to file 884/2022. According to El Financiero, it will be on April 22 when it will be determined whether to grant the definitive suspension.

It should be remembered that Section 5 South of the Maya Train is run by Grupo México and the Spanish company Acciona. It will have two stations (Tulum and Tulum Airport) and three stops (Xcaret, Puerto Aventuras and Akumal). However, various civil organizations, such as that of the French oceanographer Jean Michel Cousteau, have pointed out that construction in that area is not viable because of the karst soil on the peninsula.

Infobae

As a result, on 28 March a group of Greenpeace activists chained themselves to the machinery occupied for this stretch as a form of symbolic protest, on the grounds that the General Law on Ecological Balance and Environmental Protection (Lgeepa) was being violated, since articles 170 to 174 were being violated stipulate sanctions if the manifestation of environmental impact is not presented or is not complied with.

Similarly, a group of celebrities joined the campaign “Sélvame del Tren” to protest against the construction of Section 5 of Andrés Manuel López Obrador's megaproject, as it would affect underground rivers, cenotes and the ecological balance of the area. Eugenio Derbez, Kate del Castillo, Natalia Lafourcade, Rubén Albarran, Omar Chaparro, Ana Claudia Talancón and Bárbara Mori participated in this event.

In this regard, it should be mentioned that on March 30, a Collegiate Circuit Court on Labor and Administrative Matters ordered the withdrawal of the suspensions imposed for sections 1, 2 and 3, despite the warnings of risk to the flora and fauna of Chiapas and Yucatán.

The investment for this mega-project is 200 billion pesos and covers an area of 1,554 kilometers that will pass through the states of Tabasco, Chiapas, Campeche, Yucatan and Quintana Roo through 7 construction sections, as well as 18 stations and 12 stops.