Three more Olympic venues are ready for the Rio 2016 Games. In the balance sheet published today by the City Hall, the Arena of the Future in the Olympic Park, the Whitewater Stadium in Deodoro Sports Complex and the Golf Course already reached 100% of the work and services under the municipality’s responsibility.
Also in Deodoro, the mountain bike and BMX courses are ready as well. The International Broadcast Center was handed to the Organizing Committee in the beginning of the current month. Venues such as the three Carioca Arenas, the Aquatic Stadium and the Athletes’ Village already reached 90% of their construction. The Olympic Park as a whole reached 94%.
The evolution of these percentages are updated monthly by Rio City Hall and published at http://www.cidadeolimpica.com.br/en/construction-progress/
OLYMPIC PARK: 94%
Carioca Arena 1: 95%
Carioca Arena 2: 97%
Carioca Arena 3: 98%
Velodrome: 73%
Tennis Center: 85%
Arena of the Future: 100%
Aquatic Stadium: 96%
IBC: 100%
MPC: 91%
Hotel: 86%
GOLF COURSE: 100%
ATHLETES’ VILLAGE: 97%
DEODORO
Mountain Bike Center: 100%
Olympic BMX Center: 100%
Whitewater Stadium: 100%
Youth Arena: 70%
For more information, please contact:
olimpiada.prefeituradorio@gmail.com
As a service to our readers,Around the Rings will provide verbatim texts of selected press releases issuedby Olympic-related organizations, federations, businesses and sponsors.These press releases appear as sent to Around the Rings andare not edited for spelling, grammar or punctuation.20 Years at#1: Your best source of news about the Olympics is www.aroundtherings.com, forsubscribers only